Almost all municipalities of Aurora, except Dingalan is now served by the Aurora Electric Cooperative, Inc, (AURELCO). The AURELCO subscribed power supply from the National Power Corporation (NAPOCOR) through the latter's power station in the Sta. Rosa Grid, Sta. Rosa, Nueva Ecija with sub-station in San Isidro, San Luis serving Central Aurora, and its Power Generator Plant in Casiguran serving the DICADI areas. Dingalan's power source comes from the Nueva Ecija Electric Cooperative Company II (NECCO II) via Gabaldon, Nueva Ecija but distribution lines are installed by the AURELCO.

Within the municipalities, some remote barangays are not reached by the electrification program which left the areas without distribution power lines. Some households use portable power generators to run their appliances and lighting fixtures.

Status of Electrification

As of April 30, 2003

 

Covered

Municipality

Barangays

Consumers

Members

Covered

Energized

%

Potential

Actual

%

Signed-up

Approved

Baler

Dipaculao

San Luis

Ma. Aurora

Dinalungan

Casiguran

Dilasag

Dingalan

13

25

20

38

9

24

11

11

13

21

15

34

8

22

7

10

100

84

75

89

88

91

63

90

5,362

4,364

4,254

6,314

1,601

3,943

2,487

3,958

6,840

2,791

3,060

5,500

595

2,498

550

2,702

127

63

71

87

37

63

22

68

20

16

20

38

0

7

2

23

6,458

2,769

2,923

5,363

642

2,369

565

2,748

Total

151

130

86

32,283

24,536

76

126

23,837

Source: AURELCO